ABIC contracts · Choosing a form

ABIC Simple Works vs Major Works

The two most-used ABIC forms are built on the same foundations but carry very different amounts of contractual machinery. Choosing the wrong one costs you either protection or time.

How the ABIC suite fits together

ABIC contracts are published by Australian Building Industry Contracts, a joint venture of the Australian Institute of Architects and Master Builders. They replaced the older JCC series and share a common design: plain-English drafting, and an architect appointed as contract administrator who assesses claims, certifies payment and decides variations and extensions of time independently of both parties.

The suite is organised on two axes. The first is the scale of the contractual machinery: Major Works (MW) is the fullest form, Simple Works (SW) is a streamlined version, and Basic Works (BW) is shorter again for minor work. The second is the type of work: each form comes in a Commercial variant (suffix C) and a Housing variant (suffix H), because residential building work is regulated and needs different terms. So ABIC SW-2018 H is the Simple Works form in its housing version, and ABIC MW-2018 C is the Major Works form for commercial work.

The mistake is treating the choice as purely a question of contract value. Dollar bands do circulate in the industry, and they are indicative at best: they conflict with each other, and they say nothing about the two things that actually determine which form you need, namely how much administrative machinery the project requires and how much risk-allocation detail the parties need settled in advance.

Choosing MW for a straightforward renovation loads a small job with notice regimes and procedures nobody will follow, and unfollowed procedures are worse than absent ones because they create breaches. Choosing SW for a long, complex, multi-trade project leaves you without the machinery to deal with the events that project will actually throw up.

  • The choice is made on contract value alone, rather than complexity and administration.
  • Major Works is used on small jobs, so its notice and procedure regimes are ignored in practice.
  • Simple Works is used on complex jobs, leaving gaps when significant delay or variation events arise.
  • The Commercial variant is used for residential work, missing the mandatory statutory terms.
  • The form is chosen after the price is agreed, when the risk allocation it assumes is no longer negotiable.

How to tell which form the project needs

Start with the type of work, because that decision is not discretionary. If the work is residential building work, you need the Housing variant, and you need it to comply with the residential building legislation of the state where the work is carried out. A Commercial form used on residential work will be missing statutory terms it is required to contain.

Then assess the project rather than the price. Simple Works suits work with a short programme, a contained scope, a manageable number of trades, and few expected variations: renovations, extensions, alterations, and smaller fitouts. Major Works suits work with a long programme, staged or sequenced construction, many trades and subcontractors, provisional and prime cost allowances that will need adjusting, and a realistic expectation of significant variations, delay claims and extension of time disputes.

The practical test is to ask what happens when things go wrong. If a serious delay event occurred six months in, would you want a detailed extension of time regime with defined notice periods, or would the shorter form’s simpler provisions be adequate? If you would want the detail, use the fuller form. Machinery you never need is a minor inefficiency; machinery you need and do not have is a dispute.

Both forms are amended the same way, which is worth knowing before you commit. Every ABIC contract carries a Special Conditions schedule, referenced in the contract information schedule and taking effect through the order-of-precedence provision. That is where targeted amendments go, whether you are moving a housing contract from stage payments to monthly progress claims, adding a force majeure regime the standard form does not contain, or bringing a commercial form into compliance for residential work. Choosing the lighter form and adding the specific machinery you need is often a better answer than adopting the heavier form wholesale.

ABIC Simple Works and Major Works compared

Comparison: Simple Works (SW) against Major Works (MW).
AspectSimple Works (SW)Major Works (MW)
Intended useSmaller, contained projects: renovations, extensions, alterations, smaller fitouts.Larger, longer and more complex building projects with substantial subcontract packages.
Contractual machineryStreamlined. Fewer clauses, shorter procedures, less administrative overhead.Full. More detailed notice regimes, procedures and defined processes throughout.
Architect’s roleContract administrator, with a lighter certification and instruction load.Contract administrator, with a substantially heavier and more formalised load.
Time and delay provisionsAdequate for short programmes with few delay events.More detailed extension of time and delay machinery for staged, long-programme work.
Variations and adjustmentsSimpler valuation and instruction procedures.Fuller provisions, including more developed treatment of provisional and prime cost sums.
Administrative burdenProportionate to a small job, and realistic to actually comply with.Significant. Requires genuine contract administration resourcing to run properly.
Housing and commercial variantsSW-2018 H for residential building work; SW-2018 C for commercial.MW-2018 H for residential building work; MW-2018 C for commercial.
How it is amendedSpecial Conditions schedule, referenced in schedule 1 and given effect by the order-of-precedence clause.Identical mechanism. The same drafting approach applies to both forms.

Who this protects

Architects

You will administer whichever form is chosen. Picking machinery proportionate to the job, and to your fee for administering it, is in your interest as much as the client’s.

Builders

The form sets your notice obligations and your payment and variation entitlements. A form nobody complies with is a form that will be used against whoever complied least.

Owners & developers

The right form settles in advance how delay, variations and cost adjustments are handled, which is far cheaper than arguing about it once the work has started.

Common questions

What is the difference between an ABIC Simple Works and Major Works contract?

Both are architect-administered ABIC building contracts with the same underlying structure. Major Works (MW) is the fuller form, with more detailed notice regimes, time and variation machinery, and procedures suited to larger and more complex projects. Simple Works (SW) is streamlined for smaller, shorter, more contained projects such as renovations, extensions and smaller fitouts. The difference is the amount of contractual machinery, not the quality of the drafting.

Is the choice between ABIC SW and MW based on contract value?

Not primarily. Value bands circulate in the industry but they conflict with one another and are indicative only. The better test is the complexity of the work, the length of the programme, the number of trades, and how much administrative machinery the project genuinely needs. A high-value but simple project may suit Simple Works; a lower-value but complex one may not.

What do the H and C suffixes mean on an ABIC contract?

H denotes the Housing variant, for residential building work, and C denotes the Commercial variant. Residential building work is regulated by state legislation and requires terms the commercial forms do not contain, so ABIC SW-2018 H is the correct starting point for a residential project, not ABIC SW-2018 C.

What about ABIC Basic Works?

Basic Works (BW) is the shortest form in the suite, intended for minor building work where even the Simple Works machinery is more than the job warrants. It follows the same architect-administered model with the least contractual overhead.

Can an ABIC Simple Works contract be amended for a complex job?

Yes, and it often is. Every ABIC contract has a Special Conditions schedule, referenced in the contract information schedule and given effect through the order-of-precedence provision. Targeted Special Conditions can add the specific machinery a project needs, such as a monthly progress payment regime, a force majeure clause, or supply chain cost provisions, without adopting the whole of the heavier form.

Who publishes the ABIC contracts?

Australian Building Industry Contracts, a joint venture of the Australian Institute of Architects and Master Builders. The contracts themselves are obtained from the publisher; Special Conditions that amend them are a separate document prepared for the particular project.