Payments · Adjudication
Adjudication in Construction
The statutory fast track for construction payment disputes: how it runs, how quickly, what an adjudicator can decide, and why the answer is binding but not final.
The problem adjudication was built to solve
Construction runs on credit. A head contractor pays subcontractors and suppliers before being paid, and a subcontractor pays wages before being paid. When a payment is withheld part-way up that chain, the loss does not stay where it lands. It travels down, and businesses that have done nothing wrong run out of cash.
Before security of payment legislation, the only answer to a withheld payment was to sue. Litigation takes months at best and years at worst, and costs money the unpaid party by definition does not have. A well-resourced party could withhold payment knowing the other side could not afford to test it. Insolvency frequently arrived before judgment did.
Every Australian state and territory now has security of payment legislation that responds to this. It gives a statutory right to progress payments for construction work whether or not the contract provides for them, and a fast adjudication process in which the amount payable is decided on an interim basis and enforced immediately, without prejudice to either party’s right to have the dispute finally determined later by a court or arbitrator.
- Withheld payment travels down the contracting chain and hits parties who are not part of the dispute.
- Litigation is too slow and too expensive to protect cash flow during a live project.
- The party with deeper pockets can withhold payment knowing it will not be challenged.
- Insolvency often arrives before a court can decide who was right.
- The timetables are short and unforgiving, and a missed deadline can end an otherwise strong claim.
How the process actually runs
The sequence is broadly the same across jurisdictions, though the labels and the exact periods differ. The party owed money serves a payment claim for construction work carried out. The paying party responds with a payment schedule, stating what it proposes to pay and, critically, giving its reasons for any amount withheld. If it does not respond in time, it can become liable for the full claimed amount, and its ability to raise reasons later is restricted.
If the scheduled amount is less than the claimed amount, or nothing is paid, the claimant applies for adjudication. An adjudicator is appointed, the respondent lodges a response, and the adjudicator determines the amount payable, typically within about ten business days of accepting the application. The determination is a decision on the amount payable now. It can be registered and enforced as a judgment debt, and in most jurisdictions the grounds for resisting enforcement are narrow.
Two features are widely misunderstood. First, adjudication is interim: it decides who holds the money pending final resolution, not who is ultimately right. Either party can still litigate or arbitrate the underlying entitlement, and the determination does not create a final legal position. Second, the reasons given in the payment schedule largely fix the boundaries of the dispute. A respondent who omits a reason at the payment schedule stage will often be unable to run it in the adjudication at all.
The timetables are the most common cause of otherwise sound claims failing. They are short, they are calculated in business days, they differ between jurisdictions, and they are generally not extendable by agreement or by the adjudicator. The Western Australian regime was substantially rewritten by the Building and Construction Industry (Security of Payment) Act 2021 (WA), so material written for the earlier WA process no longer describes the current one.
Adjudication compared with court or arbitration
| Aspect | Adjudication | Court or arbitration |
|---|---|---|
| How long it takes | Weeks. The determination usually follows within about ten business days of the application being accepted. | Months to years, depending on the forum and the complexity. |
| What it decides | The amount payable now for construction work under the payment claim. | The parties’ final legal rights, including damages, defects and termination. |
| How final it is | Binding on an interim basis. The underlying dispute can still be determined later. | Final and binding, subject to appeal rights. |
| Cost | Adjudicator’s fees plus preparation. Modest relative to the amounts usually at stake. | Substantial, and frequently disproportionate to a single progress claim. |
| Evidence | Documents only. No hearing, no cross-examination, no witnesses. | Full evidence, witnesses, expert reports and cross-examination. |
| Timetable discipline | Strict statutory deadlines in business days, generally not extendable. | Timetables set by the court or tribunal, and usually adjustable. |
| Scope of the argument | Largely fixed by the reasons given in the payment schedule. | Any ground properly pleaded can be run. |
Who this protects
Builders & subcontractors
The fastest route to recovering a withheld progress payment, provided the payment claim is properly made and the deadlines are met.
Owners & principals
The payment schedule is the critical document. Reasons for withholding must be stated there, in full, and on time, or they may be lost.
Architects & contract administrators
Certification decisions and their timing feed directly into the statutory process, so the certification cycle needs to be run to time and on the record.
Common questions
What is adjudication in construction?
Adjudication is a statutory process for resolving construction payment disputes quickly. An independent adjudicator determines, on the documents, how much is payable under a payment claim. The determination is binding on an interim basis and can be enforced as a judgment debt, while leaving the parties free to have the underlying dispute finally decided by a court or arbitrator later.
How long does construction adjudication take?
Much faster than litigation. Once an adjudicator accepts the application, a determination typically follows within about ten business days, so the whole process from payment claim to determination is usually measured in weeks. The exact statutory periods differ between jurisdictions.
Is an adjudication determination final?
No. It is binding on an interim basis and enforceable straight away, but it decides who holds the money pending final resolution rather than who is ultimately right. Either party can still pursue the underlying entitlement in court or arbitration.
What happens if I do not serve a payment schedule in time?
The consequences are serious. Depending on the jurisdiction, failing to serve a payment schedule within the statutory period can make you liable for the full amount claimed and can restrict your ability to raise reasons for withholding at the adjudication stage. The payment schedule is the document that defines what you are permitted to argue about.
Can an adjudicator decide a defects or damages claim?
Only to the extent it bears on the amount payable under the payment claim. Adjudication is directed at the progress payment, not at the parties’ final rights. Broader claims for damages, defective work or wrongful termination belong in court or arbitration, although they may be relevant to valuing the claim.
Do the adjudication rules differ between states?
Yes, and the differences matter. Each state and territory has its own security of payment Act, with its own deadlines, terminology and procedural requirements. Western Australia’s regime was substantially rewritten by the Building and Construction Industry (Security of Payment) Act 2021 (WA). Always work from the Act applying to the jurisdiction where the work was carried out.
Get advice on an adjudication
Whether you are preparing a claim, responding to one, or deciding whether adjudication is the right move, advice from a registered adjudicator in five Australian jurisdictions.
Construction adjudication
Adjudication advice and representation for claimants and respondents across Australia.
ContinueSecurity of payment
Payment claims, payment schedules and strategy under each state’s security of payment Act.
ContinueIndependent adjudicator
Appointment as an adjudicator, and what parties can expect from the determination process.
Continue