Cost-Plus Residential Building Contracts
Why a commercial cost-plus contract should be checked against the residential building legislation applying to an Australian home, and how targeted Special Conditions address identified requirements in NSW and WA.
The problem with using a commercial form on a home
Cost-plus is a legitimate and often sensible way to procure residential work, where the owner pays the actual cost of the work plus an agreed margin, which suits projects where scope is genuinely hard to fix up front. The trouble may be the contract you reach for. The ABIC CP-2014 C is a commercial cost-plus contract, and a commercial form may not contain the terms required by the residential building regime applying to the project.
Every state and territory regulates residential building work, so the commercial form must be checked against, and where necessary adapted for, the relevant jurisdiction. In New South Wales the unamended ABIC CP-2014 C lacks provisions the Home Building Act 1989 (NSW) requires for residential building work. In Western Australia it lacks the acknowledgment required by section 14 of the Home Building Contracts Act 1991 (WA) for a cost-plus home building contract, and it does not expressly address the home indemnity insurance requirements in Part 3A of that Act.
- A commercial form may omit provisions required by residential building legislation.
- In NSW, gaps against the Home Building Act 1989 (NSW) for residential work.
- In WA, the missing section 14 cost-plus acknowledgment and Part 3A insurance treatment.
- Off-the-shelf residential cost-plus forms can be one-sided; a balanced alternative is scarce.
How the Special Conditions address identified cost-plus requirements
These Special Conditions adapt the ABIC CP-2014 C for residential use in versions tailored to New South Wales and Western Australia. They are designed to address identified requirements of the Home Building Act 1989 (NSW), or the section 14 acknowledgment and Part 3A home indemnity insurance requirements of the Home Building Contracts Act 1991 (WA), when correctly used with the matching form.
The approach is deliberately light-touch: it adds provisions directed to the identified requirements without rewriting the commercial bargain the parties have chosen. For builders and owners who prefer cost-plus to a fixed price, it provides a practical, balanced alternative to the standard residential cost-plus forms.
Ready-made versions are available now for New South Wales and Western Australia. A cost-plus contract for another state or territory requires a separate check against the legislation and circumstances applying there.
Standard ABIC form vs with Special Conditions
| Aspect | Standard ABIC form | With Special Conditions |
|---|---|---|
| Intended use | Commercial projects. | Residential building work in NSW or WA. |
| NSW compliance | Missing Home Building Act 1989 (NSW) provisions. | Adds provisions intended to address identified requirements of the Home Building Act 1989 (NSW). |
| WA compliance | No section 14 acknowledgment; Part 3A not addressed. | Adds the section 14 acknowledgment and addresses Part 3A insurance. |
| Extent of change | Not applicable. | Limited to the identified requirements, so the commercial cost-plus structure is preserved. |
Who this protects
Builders
Use a familiar ABIC cost-plus contract on NSW or WA residential work with provisions directed to the identified statutory gaps, rather than a one-sided off-the-shelf form.
Owners & owner-builders
A cost-plus arrangement adapted with the identified requirements of the Home Building Act 1989 (NSW) or Home Building Contracts Act 1991 (WA) in view.
Architects
A balanced cost-plus base adapted to address identified residential requirements on projects where scope is genuinely hard to fix in advance.
Common questions
Can you use a cost-plus contract for residential building work?
Yes, but the contract must be checked against the residential building legislation in the relevant state. The commercial ABIC CP-2014 C may require adaptation. These Special Conditions are designed to address the identified NSW or WA requirements when correctly used with the matching form.
Why does the ABIC CP-2014 C need Special Conditions for a home build?
It is a commercial cost-plus contract. In NSW it lacks provisions the Home Building Act 1989 (NSW) requires for residential building work; in WA it lacks the section 14 acknowledgment and does not expressly address the Part 3A home indemnity insurance requirements of the Home Building Contracts Act 1991 (WA).
How much of the contract is changed?
The amendments are limited to provisions intended to address the identified NSW or WA requirements, so the commercial cost-plus structure of the ABIC CP-2014 C is preserved.
Cost-plus or fixed price, which should I use?
Cost-plus suits projects where scope is genuinely hard to fix up front, with the owner paying actual cost plus an agreed margin; fixed price suits well-defined scopes. Where cost-plus is the right fit for a home, these Special Conditions provide an ABIC CP-2014 C option designed to address identified NSW or WA requirements when correctly incorporated and completed.
The Special Conditions that do this
Licensed, ready-to-use Special Conditions drafted by Christopher Larcos, a solicitor and architect with more than 40 years in the construction industry.
ABIC CP-2014 C Commercial Cost Plus - Residential Special Conditions
ABIC CP-2014 C NSW - Commercial Cost Plus Residential Special Conditions
$220.00AUD
- When used with the matching contract and completed correctly, these Special Conditions are intended to address identified Home Building Act 1989 (NSW) requirements. Whether they do so depends on the completed contract, incorporation, project circumstances and applicable law.
ABIC CP-2014 C Commercial Cost Plus - Residential Special Conditions
ABIC CP-2014 C WA - Commercial Cost Plus Residential Special Conditions
$220.00AUD
- When used with the matching contract and completed correctly, these Special Conditions are intended to address identified Home Building Contracts Act 1991 (WA) requirements. Whether they do so depends on the completed contract, incorporation, project circumstances and applicable law.