Special Conditions for ABIC Contracts in Tasmania
These Special Conditions have been developed to address practical limitations in standard ABIC contracts and to provide clear, workable solutions for use in real projects.
They are available for licence and may be used with either digital or paper versions of the relevant ABIC contract.
Monthly Progress Payments Special Conditions — ABIC SW 2018 H (TAS)
Start with the Monthly Progress Payments base, then add the provisions your project needs.
Monthly Progress Payments
- Locks in monthly billing instead of stage payments.
- Obliges the architect to certify each progress claim within ten business days.
Address specific project risks
- Suspends affected obligations during natural disasters, pandemics, war, or government acts; lets either party walk away after sixty continuous days of delay.
- Caps exposure to global cost shocks: only international-supply-dependent overruns above ten percent qualify, claimed on an open-book basis within twenty business days.
- The architect assesses every claim within twenty business days and adjusts the contract price; unilateral price hikes are excluded.
Your Special Conditions include
- Monthly Progress Payments
Residential Cost-Plus Special Conditions — ABIC CP-2014 C (TAS)
The ABIC CP-2014 C Commercial Cost Plus Contract is a commercial contract that, in its unamended form, is not suited to residential building work. These Special Conditions adapt it for residential projects, in a version tailored to the requirements of the relevant state or territory.